TORVALDALIGA NORD TERMAL POWER PLANT ENEL CIVITAVECCHIA

Task

Port of Civitavecchia, Italy Thermal Power Plant in Torrevaldaliga North Dredging, 1st phase Construction of Cellular Caissons for the main jetty Ballasting and rubber filling of caissons for the main jetty Dredging 2nd phase Foundation piles for crane runway

  • Strategy

    Site Supervision

  • Design

    Project Management, Work Management

  • Client

    ENEL Ingegneria e Innovazione SPA, Milano

  • Site Supervisor

    Ing. Michelangelo Lentini

  • Budget

    € 54,545,000.00

  • Completion Date

    June 20th, 2006 - January 31st, 2010

  • Tags

    Project Management, Work Management

The Challenge

THE MAIN GOAL

The site supervision activity has been supplied in order to ensure the managements of works aimed at the conversion to coal of the Torrevaldaliga Nord Thermal Power Plant in the Port of Civitavecchia.

The Goal

SERVICES DELIVERED

In particular the works have concerned:

  1. Dredging of 1st and  2nd phase;
  2. Construction of cellular caissons- main coal quay;
  3. Ballasting and rock filling of caissons on the main quay;
  4. Foundation piles for gantry girder of continuous loaders;
  5. Disposal of dredging sediments in depositing site ‘LA MATTONARA’.