PORT OF TARANTO: SAN CATALDO CONTAINER TERMINAL YILPORT
Task
San Cataldo Container Terminal - UPGRADING AND REFURBISHMENT OF THE BUILDINGS (Office Buildings, Gate, OPS Station, refurbishment of the workshop) of the SCCT SPA container terminal at Molo Polisettoriale
Strategy
For Construction design
Design
Epc Activities, Design
Client
SCCT spa S.S. 106 Ionica Molo Polisettoriale 74123 Taranto
Chief Project Manager
Ing. Michelangelo Lentini
Budget
€ 1,597,080.56
Completion Date
March 25th, 2021 - February 9th, 2024
Tags
A NEW VISION
The San Cataldo Container Terminal (SCCT), concessionaire of the areas and quay of the Molo Polisettoriale in Taranto, has started the activities of requalification and normative adaptation to allow the operativity of the existing infrastructures and plants. To this purpose, it has defined detailed technical specifications in order to make the buildings operational and has assigned to SJS s.r.l., as General Contractor (EPC FIDIC contract), the design and works execution of refurbishment works related to the buildings listed below.

Immagine 2024-09-03 094641
Immagine 2024-09-03 094641

Immagine 2024-09-03 094809
Immagine 2024-09-03 094809

Immagine 2024-09-03 095011
Immagine 2024-09-03 095011

Immagine 2024-09-03 095119
Immagine 2024-09-03 095119

Immagine 2024-09-03 095223
Immagine 2024-09-03 095223

Immagine 2024-09-03 095339
Immagine 2024-09-03 095339

Immagine 2024-09-03 095438
Immagine 2024-09-03 095438

Immagine 2024-09-03 101719
Immagine 2024-09-03 101719

Immagine 2024-09-03 101816
Immagine 2024-09-03 101816

Immagine 2024-09-03 101958
Immagine 2024-09-03 101958

Immagine 2024-09-03 102213
Immagine 2024-09-03 102213

Immagine 2024-09-03 102332
Immagine 2024-09-03 102332
SERVICES DELIVERED
- Section 1: ‘Temporary Gate Building’;
- Section 2: Building 1 (Ground Floor and Roof Floor)’;
- Section 3: ‘Building 1 (First Floor)’;
- Section 4: ‘Workshop building (part of it)’;
- Section 5: ‘Building 2 (Ground Floor only)’;
- Section 6: ‘ OPS Building’.
The interventions included in the project are the following:
- Refurbishment works, excluding structural works;
- Functionality checks of the existing technological systems, restoration, integration and replacement of parts of the system to integrate or maintain the efficiency of the existing technological systems.
During the construction works have been executed surveys using SAPR Equipment. The SJS APR pilot has a patent issued by ENAC in accordance with European regulations EASA and can carry out overflights in the presence of people, on urban residential areas and on sensitive infrastructure (highways, power plants, railway lines, etc.).
The construction works have been carried out by the company S.J.S. BUILDINGS s.r.l.