PORT OF TARANTO BULK MATERIAL AREA MOLO POLISETTORIALE
Task
Port of Taranto, Italy Redevelopment and upgrading of the Molo Polisettoriale: Bulk material terminal rehabilitation, upgrading of the quay and yards, adjustment of bulk material area and discharge water treatment plant
Strategy
Site Supervision and Safety Coordination during construction works
Design
Design
Client
Autorità di Sistema Portuale del Mar Ionio - Porto di Taranto T.C.T. spa Livorno
Chief Project Manager
Ing. Michelangelo Lentini
Budget
€ 30.102.327,14
Completion Date
November 16th, 2015 - February 7th, 2019
Tags
A NATIONAL INTEREST SITE
The project has concerned the redevelopment of the bulk material terminal with particular attention to the existing quay, the refurbishment of the yard, the construction of a new rainwater drainage network and a new treatment plant (SIN area – SITO INTERESSE NAZIONALE).

00
00

Immagine 2024-09-03 182101
Immagine 2024-09-03 182101

Immagine 2024-09-03 182134
Immagine 2024-09-03 182134

Immagine 2024-09-03 182211
Immagine 2024-09-03 182211

Immagine 2024-09-03 182241
Immagine 2024-09-03 182241

Immagine 2024-09-03 183024
Immagine 2024-09-03 183024

Immagine 2024-09-03 183717
Immagine 2024-09-03 183717

Immagine 2024-09-03 183753
Immagine 2024-09-03 183753

Immagine 2024-09-03 183840
Immagine 2024-09-03 183840

Immagine 2024-09-03 183920
Immagine 2024-09-03 183920
SERVICES DELIVERED
At the feasibility stage, an environmental characterization of the site was carried out to achieve full knowledge of soils and groundwater at different depths. The design activities include:
- Elevation of the root yard whose ground level is currently 1 m below the surrounding area;
- Paving of the yards and remaking of the road signs;
- Refurbishment of the utilities networks (electrical, lighting, fire protection) and installation of an intrusion detection system.
The rainwater drainage system consists of a pipe network which collects and carries waters to a pumping station which raises the water, flowing through a screen, up to a tank where the first 5 mm of any rainfall is separated and stored. This water will be treated within 48 hours. It will be subject to a process of sedimentation, desolation and filtering, in compliance with the Italian law.
The further rainfall will be stored in a settling tank for as long as it takes to the sand and oil particles, potentially present in the run-off rainwater, to sediment for gravity before being discharged into the sea.