PORT OF BRINDISI REINFORCEMENT OF “ADMIRAL MILLO WHARF”, SAILORS’ MONUMENT AND CHANNEL PIGONATI

Task

Port of Brindisi, Italy Reinforment of ""Admiral Millo wharf"" (1st LOT); special maintenance anche reinforcement of wharfs nearby Sailors' Monument and of Channel Pigonati (2nd LOT)

  • Strategy

    Preliminary design, Detail Design, For construction design and Safety Coordination during design phase

  • Design

    Design

  • Client

    Autorità di Sistema Portuale del Mar Adriatico Meridionale (ex Autorità Portuale di Brindisi)

  • Chief Project Manager and Site Supervisor

    Ing. Michelangelo Lentini

  • Budget

    € 7,587,452.64

  • Completion Date

    November 6th, 2009 - May 26th, 2010

  • Tags

    Design

The Challenge

THE PHASES

The project is divided in two phases:

I LOT: Reinforcement of Admiral Millo wharf;

II LOT: Special maintenance and reinforcement of wharfs nearby Sailors‘ Monument and of Channel Pigonati.

The Goal

SERVICES DELIVERED

  1. The restoration, consolidation, and operational rehabilitation of the existing quay inside the historical inner port of  Brindisi;
  2. The Retaining works and structural repairs in order to increase the safety of the quay wall structures;
  3. The design of local stone pavement restoration;
  4. The Harbour functional installation (bollards, fenders);
  5. The public lighting and other urban equipment.
  6. The Works Management involved both lots, for the works and for the static tests, completed in December 2016, and the technical administrative tests, completed on 1st June 2017.