METEORIC WATER DRAINAGE SYSTEM UPGRADING PORT OF TARANTO

Task

Meteoric water drainage system upgrading works and new discharge manifold for discharge waters in the Molo Polisettoriale Container Terminal - Taranto

  • Strategy

    Detail design, For construction Design, Safety Coordination during design phase

  • Design

    Project Managemen, Design

  • Client

    T.C.T. spa - Scali Cerere n. 9 57122 LIVORNO

  • Chief Project Manager and HSE Manager

    Ing. Michelangelo Lentini

  • Budget

    € 1,301,508.31

  • Completion Date

    February 15th, 2013 - April 2nd, 2013

  • Tags

    Design, EPC Activities

The Challenge

Meteoric water drainage system upgrading works and new discharge manifold for discharge waters in the Molo Polisettoriale Container Terminal – Taranto