ARCELOR MITTAL RAINWATER

Task

Rainwater system redevelopment in iron and steel plant of Taranto, implementation of environmental restoration measures prescribed by the Integrated Environmental Authorisation (AIA). Project Management, Site Supervision

  • Strategy

    Project Management

  • Design

    Project Management

  • Client

    ARCELOR MITTAL Italia spa

  • Capo Progetto Project Director

    Eng.. Michelangelo Lentini

  • Budget

    € 80,000,000.00

  • Completion Date

    April 15th, 2019 - March 13th, 2020

The Challenge

RAINWATER SYSTEM REDEVELOPMENT

The Services provided include ‘engineering services-design, procurement and project management’ aimed to support the technical offices throughout the rainwater system redevelopment in Taranto Factory.

The project includes the following interventions:

  1. The environmental and anthropic impacts;
  2. The interferences between the new constructions and the existing network/utilities, drawing up a preliminary surveys plan to be performed before starting the design activities, aimed to reduce unexpected issues in work-site area of Taranto;
  3. The interferences between the AM Italia S.p.A. ordinary activities and the construction works;
  4. The achievement of high safety standard levels during the construction works, with particular attention to employee health and safety measures.

 